临江青山水库工程


一、项目简介
1.项目概况:按照《临江市城区供水规划>预测,2010年城区需水量为1.8万立方米/日。现供水能力为1.25万立方米/日,而水源污染问题却日益严重。随着城市建设发展,头道沟河干流已不适宜做为城区生活饮用水源,另辟新水源已成当务之急。青山水库位于鸭绿江头道沟河支流青沟河下游,工程规模为水库兴利库容13l万m3,死库容3l万m3,防洪库容53万m3,总库容215万m3,水库正常蓄水位411.75m,P=0.2%校核洪水位412.36m,P=2%设计洪水位411.75m。该工程建设的主要任务是城市供水,兼顾灌溉、防洪等。
2.合作方式:合资
3.项目总投资:230万美元
4.需外方投资内容:资金、设备
5.建设地点:鸭绿江头道沟河支流青沟河下游
6.占地面积和建筑面积:占地面积10200m2,建筑面积2200m2
7.预计经济效益:年净利润266.58万元
8.项目进展情况:立项,吉计农字(1998)l028号
二、中方概况
1.企业名称:吉林省临江市水电股份有限公司
法定地址:吉林省临江市鸭绿江大酒店
法定代表人:张雁鸣
2.所有制形式:股份制
3.企业概况:临江市水电股份有限公司现有员工800人,注册资本3000万元,现有资产6700万元,年平均实现利税8l0万元。临江地区水电资源非常丰富,大小水电站几十家,装机容量达36393kw,全年发电5200万度。公司下属两个工厂:宏业高温材料厂,年产3000吨镁碳砖;冶炼厂年产3500吨工业硅,出口日本。
4.可为项目提供的建设和生产条件:土地、厂房、技术、部分资金
5.联系方法:
通讯地址:吉林省临江市鸭绿江大酒店
邮政编码:134600
项目联系人:颜世才、张雁鸣
电话:86—439—5222867 5231538
传真:86—439—5222188

Linjiang Qingshan Reservoir Project

I. The Brief Introduction of the project
1. Survey of project:
According to《Program of water supply for city proper》
processing need water of the city proper in 2010 is 18000 m3 a day. Now water supply is 12500 m3 per day and water source of pollution is growing serious with the city development. The main stream of the first ditch river is not fit for drinking water of city proper. The urgent mater is to open up another new one. Qingshan reservoir is located at the lower reaches of the first ditch river Yalujiang. The project scope is as follows: beneficial storage capacity of reservoir 1.31 million m3 , dead storage 0.31 million m3, p=0.2%, the checked flood level 4.1236 m,p=2%, designed flood level 411.75 m, the main task of the project is for city water supply, irrigation and controlling flood.
2. Cooperative patterns: Joint venture
3. Estimated total investment: USD 2.3 million
4. The content of requisite foreign investment: Capital, equipment
5. Construction place: at the lower reaches of Qing Ditch River of the first Ditch River branch on Yalu River
6. Occupied area and construction area: Occupied area: 10200 sq.m, construction area: 2200 sq.m
7. Estimation of economic benefit: Annual net profits RMB 2.6658 million yuan
8. Process in the project: The feasibility study report has been registered and approved through the document of JJN Zi,(1998) No.1028
Ⅱ.Survey of partner
1.Enterprise name: Linjiang City Water and Hydropower Co.,
Ltd
Legal address: Linjiang City Yalujiang Hotel, Jilin Province
Representative personage: Yan shi-cai
2.the form of ownership: Stock system
3.Enterprise survey: Hydropower Co.,Ltd.. has 800 staff,
registered capital RMB 30 million yuan, existing assets RMB 67 
million yuan, annual average profit tax 8.1 million yuan. 
Linjiang region has abundant hydropower resource, several ten
Hydropower stations, the installed capacity of waterpower is 
up to 36393 kw, annual generated energy 52 million kwh, there
are 2 attached factories: Hongye High Temperature material
factory, annual production of magnesium carbon brick 3000 tons. 
Industrial silicon 3500 tons in the smeltery and are exported 
to Japan.
4.Existing matching production conditions supplied: land,
factory, partial capital 
5.Contact way:
Add: Yalujiang Hotel, Linjiang City, Jilin Privince
Post code: 134600 
Liaison and post: Liu Kai-hua Zhang yan-ming
Tel: 86-439-5222867 5231538
Fax: 86-439-5222186
 